Wahlert Renovation Updates

 

April 2017

The work continues at Wahlert Catholic with ground-level, hallway ceiling demolition as well as plumbing, electrical and structural changes in the gym and locker rooms. Every opportunity to maximize time and efficiency has been captured in preparation for large-scale reconstruction taking place this summer. While students were Spring Breaking, the cafeteria asbestos flooring was removed. Temporary walls have been created to facilitate curtain wall removal in the weight room and cafeteria. Roof replacement in the gym and painting in the O’Connor Activity Center (OAC) is underway. The west wing, bridge, kitchen and cafeteria remain to be completed by the target project end date of November 1, 2017. 

Projects Completed to Date:

  • Central stairs
  • East wing classrooms
  • Chapel
  • Theater
  • Library
  • Conference Room